How to Set Yokogawa Transmitter with Communicator?
Yokogawa, I believe everyone knows it very well, and knows that it is a leading company in the field of electrical and electronic engineering in the world. Due to the high requirements for productivity, efficiency, speed and quality, Yokogawa products have a good reputation and market share in the field of industrial automation. Yokogawa not only has a large market share in the pressure transmitter market, but also has a good sales volume of temperature transmitters. But when it comes to debugging settings for Yokogawa transmitters, many parts are not very clear. Today, we will take the Yokogawa temperature transmitter YTA70 as an example, and tell you how to debug and set it with a hand-held communicator.
1. How to modify the range of the Yokogawa temperature transmitter YTA70J with the 475 Communicator. Specific steps are as follows:
1. Power on, connect the 475 Communicator to the Yokogawa transmitter, and select HART.
2. After the communication is successful, select Online, then the function menu that can be set for the Yokogawa temperature transmitter YTA70J will be displayed.
3. Click 1.device setup
4. Select and click 3.basic setup, and then click 2.zero/span set to modify the zero and span settings.
2. How to modify the damping of the Yokogawa temperature transmitter YTA70 with the 475 Communicator. Specific steps are as follows:
Steps 1 and 2, same as above.
3. Click 1.device setup
4. Click 3.basic setup
5. Select and click 3.damp to modify the damping.
3. How to use Yokogawa temperature transmitter YTA70 to set several wires with 475 hand communicator. Specific steps are as follows:
Steps 1 and 2, same as above.
3. Click 1.device setup
4. Click 4.detailed setup
5. Click to select 1.calibration
6. Click to select 1.sensor
7. Click to select 1.process sensor
8. Click to select 1.sensor setup
9. Click to select 4.sensor connection, 4 wire to set several wires.
4. How to use the 475 Communicator to modify the graduation number of the Yokogawa temperature transmitter YTA70. Specific steps are as follows:
Steps 1 and 2, same as above.
3. Click 1.device setup
4. Click 4.detailed setup
5. Click to select 1.sensor
6. Click to select 1.process sensor
7. Click to select 1.sensor setup
8. Click to select 1.sensor type, t100 iec 751 to modify the graduation number.
5. How to use Yokogawa temperature transmitter YTA70 to test the settings with the 475 hand communicator. Specific steps are as follows:
Steps 1 and 2, same as above.
3. Click 1.device setup
4. Click 2.diag/service
5. Click to select 1.sensor
6. Click to select 2.simulation/test
7. Click to select loop test to set the loop test.
The above is how the Yokogawa temperature transmitter YTA70 uses the 475 hand-held communicator for preliminary settings